INDIAN STATE : MEGHALAYA
Economic infrastructure
Power
The development of the Power Sector
in the state of Meghalaya is presently moving in the
right direction so that the availability of affordable,
reliable and quality power is ensured to the people
of the state in the near future. The state's energy
requirement in the year 2005-06 was 1228.43 MW and the
peak load was 190.90 MW during the same year.
During the year 2005-06 the per capita
consumption in Meghalaya was 313.442 units. Power generation
in the state in the same year was 516.72 MU and the
revenue generated was 23643.21 lakh.
Existing Power Stations
Meghalaya has following Power generating
stations:
Source: Meghalaya State Electricity
Board
Rural Electrification
Places like Sumer, Byrnihat and other
villages numbering only 261 enjoyed electricity. Today
the number of villages electrified has gone up to 4217
while the number of consumer up to about 2,08,871.
The current status of villages that
are electrified in meghalaya during the year 2005-06
are
Status of villages electrified in meghalaya as on 31.03.2006
District |
No. of Villages
as per Census 2001 |
No. of Villages
Electrified as on 31.03.06 |
East Khasi Hills |
920 |
887 |
West Khasi Hills |
924 |
583 |
Jaintia Hills |
467 |
422 |
Ri Bhoi |
543 |
495 |
East Garo Hills |
864 |
556 |
West Garo Hills |
1469 |
943 |
South Garo Hills |
595 |
291 |
Total |
5782 |
4177 |
Source: Meghalaya State Electricity Board
Transmission & Transformation
scheme
Considering the rapid growth of load
demand in the State, Meghalaya State Electricity Board
(MeSEB) formulated a scheme for taking up the augmentation
and construction work of 132KV/220KV Grid sub-stations
and transmission lines.
The schemes being implemented are as follows:
A. |
Construction of the 132 KV transmission
line from Sarusajai in Assam to Byrnihat in Meghalaya
|
|
The project cost of the line
is Rs. 1045.00 lakhs and is funded under Non-lapsable
Central Pool of Resources for North Eastern Region
(NLCPR). Dept. for development of NorthEastern Region
(DONER) at the cost of Rs. 9.78 crores approved
the project. The Meghalaya portion of the line has
been completed and commissioned on 20-05-05. The
Assam portion of the line is being taken up by Assam
State Electricity Board (ASEB) and the work is in
progress. This line on completion will enable the
state to draw an additional 80 MW of power. |
B. |
Construction of the 132 KV transmission
line from the Me.S.E.B. Sub-Station at Khliehriat
to PGCIL Sub-Station at Khliehriat
|
|
The project is funded under
Non-lapsable Central Pool of Resources for North
Eastern Region (NLCPR) at the estimated cost of
Rs. 286.00 lakhs. The work is in progress. |
C. |
Construction of the 132 KV double
circuit transmission line from Agia in Assam to
Nangalbibra in Meghalaya |
|
The revised project cost of
the line is Rs. 4693.65 lakhs. The NEC funds the
project. The forest clearance for both the Meghalaya
and Assam portion of the line had been obtained
and forwarded to the North Eastern Council (NEC).
The Eleventh Finance Commission (EFC) memorandum
for the construction of line had been submitted
to the North Eastern Council (NEC) in January 2006.
|
D. |
Construction of
220 KV transmission line from Misa in Assam to Byrnihat
in Meghalaya along with the construction of the
220 KV/132 KV, 1 x 100 MVA at Byrnihat |
|
The Detailed Project Report
was cleared by Central Electricity Authority (CEA)
and the work is to be executed by a Joint Venture
between Me.S.E.B. and Power Grid Corporation of
India Limited (PGCIL). MOU for this project was
signed on the 08-09-05-. The project is scheduled
to be completed by March 2009 and the project cost
of the scheme is Rs. 243 Crores. |
E. |
The 132/33 KV Sub-Station at
NEIGHRIMS was commissioned on 6th May 2005 |
F. |
Construction of the 132 KV/33
KV Sub-Station at Norbong, Byrnihat |
|
The project cost of the work
is Rs. 465.00 lakhs. The work is in progress. |
G. |
Construction of the 132 KV/33
KV Sub-Station at Khliehriat |
|
The project cost of the work
is Rs. 84.00 lakhs. The work has been completed
in all respect. |
H. |
Augmentation of
the 132 KV/33 KV Sub-Station at Nangalbibra |
|
The project cost of the work
is Rs. 85.00 lakhs. The work involves the augmentation
of the Sub-Station from 17.5 MVA to 25 MVA and the
work is in progress. |
Other transmission
line works being taken up are |
A. |
LILO of 132 KV Stage IV - Sarusajai
at Umtru Power Station
NEC under NEC 10th Plan at the project cost of Rs.
3.87 crores funds this project and the work is in
progress. This line will improve the grid network
and derive optimum benefit from the 100 MVA transformation
capacity installed at Sarusajai to cater to the
demand at Byrnihat. |
B. |
132 KV Leshka Khliehriat line
|
|
The project was approved for
funding under ACA. The NIT for the work is being
issued and the material procurement work is in progress.
|
C. |
2nd circuit of the 132 KV single
circuit line from Stage III Power Station to Stage
IV Power Station |
|
The project will be funded by
NEC under the NEC 10th Plan. The revised project
cost is Rs. 458.00 lakhs and the detailed project
report had been submitted to NEC in January 2006.The
project is scheduled to be completed by March 2007.
|
D. |
Construction of the 132 KV/33
KV Sub-Station at Lumshnong with LILO of the 132
KV Khliehriat - Panchgram line |
|
The DONER at the cost of Rs.
4.63 crores approved the project. The work has been
completed as per scheduled.This project will cater
to the growing industrial load demand around Lumshnong
and will improve the quality of domestic power supply.
|
Sub-Transmission
and distribution schemes |
A. |
Distribution master plan |
|
This project is taken up in
order to improve the existing transmission system
and to provide quality and reliable power to the
people of the state. The project will also enable
additional sale of energy and reduce the energy
losses that in turn would generate additional revenue
income to the Board. The project is funded under
Non-lapsable Central Pool of Resources for North
Eastern Region (NLCPR) at an approved cost of Rs.
24.00 crores. The target date of completion of the
project is June 2006. |
B. |
Improvement of power
supply in Tura |
|
The project is funded under
Non-lapsable Central Pool of Resources for North
Eastern Region (NLCPR) at an approved cost of Rs.12.03
crores and the work was completed in the month of
October 2005. |
|